Optimasi Waktu dan Biaya pada Pelaksanaan Proyek Peningkatan Jalan Bina Bakti Kelurahan Gunung Seteleng Kabupaten Penajam Paser Utara dengan Metode Time Cost Trade Off (TCTO)

Time and Cost Optimization in The Implementation of the Improvement of the Bina Bakti Road of Gunung Seteleng Kabupaten Penajam Paser Utara with Time Cost Trade Off (TCTO) Method

Authors

  • Irna Hendriyani Universitas Balikpapan
  • Reno Pratiwi Universitas Balikpapan
  • Nour Qadri Universitas Balikpapan

DOI:

https://doi.org/10.36277/transukma.v3i1.72

Keywords:

Optimization, Time Cost Trade Off, Addition of Overtime Working Hours, Addition Workforce, Penambahan Jam Kerja Lembur, Penambahan tenaga kerja

Abstract

Tolok ukur keberhasilan suatu proyek dapat dilihat dari waktu penyelesaian yang singkat dengan biaya yang minimal tanpa meninggalkan mutu hasil pekerjaan. Proyek Peningkatan Jalan Bina Bakti Kelurahan Gunung Seteleng Kabupaten Penajam Paser Utara dipilih sebagai objek penelitian dengan panjang jalan 569 Meter dan anggaran proyek senilai Rp.1.222.038.477,10 karena proyek ini mengalami keterlambatan. Salah satu upaya mengoptimalkan proyek yang sering digunakan adalah dengan metode TCTO (Time Cost Trade Off), Metode ini digunakan untuk menghitung perubahan waktu dan biaya pelaksanaan proyek paling optimum. Dengan menggunakan penambahan jam kerja lembur dan penambahan tenaga kerja. Waktu pelaksanaan proyek Peningkatan Jalan Bina Bakti selama 54 hari kalender. Berdasarkan hasil penelitian waktu dan biaya paling optimum setelah penambahan jam kerja lembur didapatkan total biaya optimum Rp.1.220.695.370,54 dan durasi crashing 42,4 hari dengan efisiensi biaya 0,11% dan efisiensi waktu 13,47%. Untuk penambahan tenaga kerja didapatkan waktu dan total biaya optimum  Rp.1.215.485.807,44 dan durasi crashing 37,8 hari dengan efisiensi biaya 0,54% dan efisiensi waktu 22,86%. Dari hasil penelitian ini didapatkan bahwa penambahan tenaga kerja lebih efisien dibandingkan dengan penambahan jam kerja lembur dan mendapatkan keuntungan biaya lebih besar.

 

Kata Kunci : Optimasi, Time Cost Trade Off, Penambahan Jam Kerja Lembur,  Penambahan tenaga kerja

 

The benchmark for the success of a project is seen from the short completion time with minimal costs without leaving the quality of the work. The Bina Bakti Road Improvement Project in Gunung Seteleng Subdistrict, Penajam Paser Utara Regency was chosen as the research object with a road length of 569 meters and the project budget valued at Rp.1,222,038,477.10 this project experienced a delay. Efforts to optimize one of the elements that will affect project control even two other elements, such as time, cost and resources. One of the optimal steps that is often used to overcome project delays is the method of TCTO (Time Cost Trade Off), this method is an attempt to exchange time and costs. This research calculates the most optimum change in time and cost of project implementation. By using additional hours of overtime and additional workforce. The time for implementing the Bina Bakti Road Improvement project for 54 days. Based on the results of the most optimum time and cost research after the addition of overtime working hours, the optimum total cost of Rp.1,220,695,370.54 and 42.4 days of crashing duration with cost efficiency 0.11% and time efficiency 13.47%. And for the addition of workforce, the optimum time and total cost of Rp.1,215,485,807.44 and the crashing duration of 37.8 days were obtained with cost efficiency of 0.54% and time efficiency of 22.86%. From the results of this study, it can be seen that the addition of labor is more efficient compared to the addition of overtime working hours and obtaining greater cost benefits. 

 

Keywords: Optimization, Time Cost Trade Off, Addition of Overtime Working Hours, Addition Workforce

Author Biographies

Irna Hendriyani, Universitas Balikpapan

Prodi Teknik Sipil Universitas Balikpapan

Reno Pratiwi, Universitas Balikpapan

Prodi Teknik Sipil Universitas Balikpapan

References

Ali, Tubagus Haedar, 1995, Prinsip-prinsip Network Planning, Penerbit PT, Gramedia, Jakarta.
Clifford F, Gray dan Erik W Larson, 2007, Manajemen Proyek Proses Manejerial, Edisi Ketiga, Penerbit ANDI, Yogyakarta.
Dipohusodo, I. 1995, Manajemen Proyek dan Konstruksi. Edisi ketujuh, Penerbit Kanisius Yogyakarta.
Eddy, Herjanto, 2003, Manajemen Operasi, Grasindo, Jakarta.
Elfira Safitri, Sri Basriati, Riska Wulandari, dan Zukrianto. 2019. Analisis Optimasi Biaya dan Waktu dengan Metode PERT dan TCTO (Studi Kasus: Proyek Pembangunan Jembatan Sei Merangin Kabupaten Kampar). Prosiding Seminar Nasional Teknologi Informasi, Komunikasi dan Industri (SNTIKI) 11 Fakultas Sains dan Teknologi, UIN Sultan Syarif Kasim Riau. ISSN (Printed): 2579-7271. ISSN (Online ) : 2579-5406. November 2019.
Ervianto, W. I, 2003, Manajement Proyek Konstruksi, Penerbit ANDI, Yogyakarta
Husen, A, 2001, Manajemen Proyek Edisi I Revisi, Andi Offset, Yogyakarta.
Ibrahim, B, 2001, Rencana dan Estimate Real of Cost, Bumi Aksara, Jakarta.
Isra, Saiful Husin, dan Fachrurrazi. 2019. Model Time-Cost Trade Off untuk Pekerjaan Kolom Utama
di Kabupaten Aceh Selatan. Journal of The Civil Engineering Student Vol. 1. No. 3, Desember 2019, Halaman 98-104. ISSN 2685-0605.
Johan, dkk, 1998, Trade-Off Waktu dan Biaya Pada Proyek Konstruksi Studi Kasus Pada Proyek Kantor Bank Metro, Jurnal Teknik Sipil F.T. Unair, No. 3. Surabaya.
Keputusan Menteri Tenaga Kerja dan Transmigrasi Republik Indonesia. NOMOR KEP. 102/MEN/VI/2004. Waktu Kerja Lembur Dan Upah Kerja Lembur.
Kerzner, Harold, 2006, Project management, A Systems Approach to Planning Scheduling and controlling, Published by jhon wiley & Sons inc. USA.
Luthan, Putri Lynna A dan Syafriandi, 2005, Aplikasi Microsoft Project Untuk Penjadwalan Kerja Proyek Teknik Sipil, Penerbit ANDI, Yogyakarta.
Nugraha, P, dkk,1985, Manajemen Proyek Konstruksi 1, Penerbit Kartika Yudha, Surabaya.
Soeharto, Imam, 1997, Manajemen Proyek dari konseptual sampai oprasional Erlangga, Jakarta.
Sofyan, Badri, 1997, Dasar-dasar Network Planning (Dasar-dasar Perencanaan Jaringan Kerja, Rineka Cipta, Jakarta.
Sultan Syah, Mahendra, 2004, Manajemen Proyek Kiat Sukses Mengelola Proyek, Gramedia Pustaka Utama, Jakarta.
Tjaturono, 2006, manajement Konstruksi, Bahan Kuliah Pascasarjana Magister Teknik ITN Malang.

Downloads

Published

2020-12-22